Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables?
.png)
a. Design?
b. Programming?
c. In-house testing?
What weaknesses are inherent in this estimatingapproach?