Develop a net material requirements plan for the TOL and HQ file cabinets in the previous problems assuming a current on-hand finished goods inventory of 100 TOL cabinets. The lead times are given below.
Painting and final assembly of both HQ and TOL requires 2 weeks.
Both cabinet frames and lock assembly require 1 week for manufacturing.
Both drawer assemblies require 2 weeks for assembly.
Both sliding assemblies require 2 weeks for manufacturing.
Bearings require 2 week to arrive from the supplier.